Investigating a claim about resource complexity measure

Autor: H.R. Yousefzadeh
Jazyk: angličtina
Rok vydání: 2021
Předmět:
Zdroj: Iranian Journal of Numerical Analysis and Optimization, Vol 11, Iss 2, Pp 401-405 (2021)
Druh dokumentu: article
ISSN: 2423-6977
2423-6969
DOI: 10.22067/ijnao.2021.70437.1034
Popis: The utilization factor (UF) measures the ratio of the total resources’ amount required to the availability of resources’ amount during the life cycle of a project. In 1982, in the journal of Management Science, Kurtulus and Davis claimed that “If two resource-constrained problems for each type of resource have the same UF’s value in each period of time, then each problem is subjected to the same amount of delay provided that the same sequencing rule is used (If different tie-breaking rules are used, a different schedule may be obtained)”. In this paper, with a counterexample, we show that the claim of authors cannot be justified.