A Purely Proactive Scheduling Procedure for the Resource-Constrained Project Scheduling Problem with Stochastic Activity Durations

Autor: Erik Demeulemeester, Patricio Lamas
Rok vydání: 2014
Předmět:
Zdroj: SSRN Electronic Journal.
ISSN: 1556-5068
DOI: 10.2139/ssrn.2464056
Popis: The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource-constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure outperforms two other published methods, assuming different robustness measures. ispartof: Journal of Scheduling vol:19 issue:4 pages:409-428 status: published