EOR RMP: Addressing Key Risks Through Sound Reservoir Management

Autor: Ramli Ibrahim, Tomasso Ceccarelli, Willem Sepulveda, Prashanth Nair Kumaran, Dipak Mandal, Walter Sifuentes, Juan Carlos Moreno, Thierry Chabernaud
Rok vydání: 2018
Předmět:
Zdroj: Day 2 Wed, October 24, 2018.
Popis: This paper aims to describe the overall EOR GASWAG concept with some of the key findings after first phase execution and some of the measures taken to maintain the project within the planned OPEX to remain economic. Secondly, to describe a comprehensive reservoir management plan which includes a fit for purpose data acquisition plan and more importantly how the remaining challenges are addressed through the RMP optimization to maximize recovery. Finally, this paper outlines the main key challenges to be faced once the injection phase kicks off, highlighting the surveillance and monitoring strategies to overcome them.