Intensification of 330/400 kV power transmission in the back-to-back project connecting Russia and Finland

Autor: V. I. Galanov, G. G. Prochan, Yu. S. Kraichik, L. A. Koshcheev, L. L. Balyberdin, M. I. Mazurov
Rok vydání: 2004
Předmět:
Zdroj: Power Technology and Engineering. 38:365-369
ISSN: 1570-1468
1570-145X
DOI: 10.1007/s10749-005-0014-0
Popis: It is shown that the fourth converter unit with a capacity of 350 MW commissioned in 2000 at the Vyborg back-to-back direct-current converter station connecting the power systems of Russia and Finland increased the total installed power of the converter units to 1400 MW. The circuitry of the converter station and its connections permits two independent transmissions through the Vyborg substation with mutual redundancy and with allowance for the requirements of the receiving power system with respect to the maximum power of each transmission. Normal and emergency operating conditions are described. Difficulties encountered in the course of the work and measures taken for their elimination are discussed.
Databáze: OpenAIRE