Phase I and Phase II Archaeological Data Recovery at Five Sites for the Pinal West to Pinal Central Extra-High Voltage Transmission Line Project, near Casa Grande, Pinal County, Arizona

Autor: Brin, Adam
Jazyk: angličtina
Rok vydání: 2013
Předmět:
DOI: 10.6067/xcv8428045
Popis: Salt River Project Agricultural Improvement and Power District (SRP) has planned and partially constructed an 88-mile-long 500-kV extra-high-voltage transmission line linking the Pinal West, Duke, Pinal Central, Abel, and Dinosaur substations (Arizona Corporate Commission Certificate of Environmental Compatibility, Case No. 126) in south-central Arizona. The transmission line between the Dinosaur and proposed Pinal Central substations has already been constructed; the portion connecting the proposed Pinal Central and Pinal West substations has not been constructed yet. This report presents the results of Phase I data recovery (extent testing) and Phase II data recovery within a 40-m-wide (130 ft) corridor at three sites located on privately owned lands between the Pinal Central and Pinal West substations and at two sites located within the boundary of the proposed Pinal Central Substation. The sites are situated in central Pinal County south and east of the town of Casa Grande. Logan Simpson Design Inc. (LSD) completed the fieldwork between November 2011 and January 2012.
Databáze: OpenAIRE