Construction of KEKB vacuum system: installation of vacuum chambers

Autor: M. Sato, Hiromi Hisamatsu, Shigeki Kato, Masayuki Shimamoto, Yusuke Suetsugu, Mitsuru Shirai, Ken-ichi Kanazawa
Rok vydání: 2001
Předmět:
Zdroj: Applied Surface Science. :720-723
ISSN: 0169-4332
DOI: 10.1016/s0169-4332(00)00772-8
Popis: The operation of the KEKB accelerator at KEK started on December 1998 after about 4 years’ construction. More than 2000 vacuum chambers and their attachments were installed progressing through some stages in last 2 years. Each stage was set with specified procedure and under careful quality control. The average base pressure in the order of 10−8 Pa just before the commissioning, and the following decrease of photon stimulated gas desorption proved the validity of our procedures.
Databáze: OpenAIRE