Autor: |
WILSON, D D, FREER, R, PENMAN, A, DOUGLAS, T H, TATTERSFIELD, J, ELDRIDGE, J G, WARDLE, D G, SIMS, G P, CIRIA, SWANNELL, N G, MCCONNELL, M J, ROSSINELLI, F, PATERSON, T J M, HANNAH, I W |
Zdroj: |
Proceedings of the Institution of Civil Engineers: Water Maritime and Energy; September 1995, Vol. 112 Issue: 3 p268-273, 6p |
Abstrakt: |
DISC1JSSION Proc. Instn Civ. Engrs Wat., Marit. &Energy, 1995, 112, Sept., 268-273 Carhuaquero Hydroelectric Project F. Rossinelli, G. P. Sims and D. G. Wardle D. D. Wilson, Consultant Engineering Geologist The paper states that:' the feasibility work was mainly a desk study earlier reports', and ' an of interim report was required three months '. A in definitive report was prepared later with minimal further site investigations.How was the design effected, and how were valid tender documents prepared with such minimal and inadequate subsurface investigations?How did the authors' competitors prepare bids? 92... |