Autor: |
Reeves, John D., Eveleigh, Tim, Holzer, Thomas, Sarkani, Shahryar |
Zdroj: |
2012 IEEE International Systems Conference SysCon 2012; 1/ 1/2012, p1-8, 8p |
Abstrakt: |
Risk identification during the early design phases of complex systems is commonly implemented but often fails to result in the identification of events and circumstances that truly challenge project performance. Inefficiencies in cost and schedule estimation are usually held accountable for cost and schedule overruns, but the true root cause is often the realization of programmatic risks. A deeper understanding of frequent risk identification trends and biases pervasive during space system design and development is needed, for it would lead to improved execution of existing identification processes and methods. [ABSTRACT FROM PUBLISHER] |