Eti Copper Siirt flotation plant revision studies.

Autor: Kara, Yaşar, Tatar, Ali, Hasyamanlar, Ahmet
Předmět:
Zdroj: Physicochemical Problems of Mineral Processing; 2023, Vol. 59 Issue 5, p1-8, 8p
Abstrakt: Several optimization studies were made to increase metal recovery and reduce operational costs of the concentrator in Siirt Madenköy copper mine. In consequence of these studies, effects of the changes in operating parameters, cost and plant recovery will be examined at this article. In this article, we will discuss two important revision studies, which are (i) replacement of 500 mm hydrocyclone set used in ball mills with 350 mm of hydrocyclone set, (ii) replacing the present Ball Mill with a SAG mill. Correspondingly elimination of the crushing and screening plant, (iii) increasing the scavenger cells from 4 to 6 by the addition of 2 more cells. In consequence with this feeding the middling tail to the increased scavenger cells which was treated as a part of final tail before this change. We will examine the effect of all these changes to the final recovery, concentrate grade and final cost. [ABSTRACT FROM AUTHOR]
Databáze: Complementary Index