Simulating operation of power units 1 and 2 at Novovoronezh NPP II with two electrical feed pumps disabled and the backup pump not enabled

Autor: Igor N. Gusev, Aleksandr P. Vorobyev, Mikhail N. Kozlovsky, Sergey P. Padun
Jazyk: angličtina
Rok vydání: 2021
Předmět:
Zdroj: Nuclear Energy and Technology, Vol 7, Iss 3, Pp 187-194 (2021)
Druh dokumentu: article
ISSN: 2452-3038
DOI: 10.3897/nucet.7.72394
Popis: Introduction. The article analyzes the operation of Unit 1 and 2 of Novovoronezh Nuclear Power Plant II (equipped with VVER-1200 reactors) with two electrical feed pumps disabled and the backup pump not enabled. These operating conditions are subsequently simulated using the power unit model software-hardware package (PUM SHC) developed by LLC IF SNIIP ATOM. Research objectives. The objective of this work was to check the reliability of the forecasts of changes in the power unit parameters obtained using the PUM SHC, based on operational data. Methods. The simulated power unit parameter changes in transient conditions were in good agreement with the data collected in real tests. During the simulation, the power unit dynamic stability was preserved, i.e., the operational parameters were within the design limits and did not exceed the protection operation set points. Results. The results of the work suggest the possibility of using current NPP power unit simulations: for developing proposals for adjusting the operation control algorithms in case of malfunctions and emergency modes with the main equipment shutdown and power unit protection actuation; and for verifying design solutions for updating the power unit systems, which are associated with the use of new equipment or changes in flow diagrams. Conclusion. Current power unit models can be applied both for existing power units and for new ones that are being commissioned.
Databáze: Directory of Open Access Journals