Implementation of system installation risk on engine room module aims to anticipate ship production delays. However, in its implementation, there is the problem of ship delivery delays in various shipbuilding companies. This research will analyze t
Externí odkaz:
https://doaj.org/article/3abc198c83d24b8ca1c023cc1795b4ec
Risk Analysis of the Causes of Delay in Ship Construction (Case Study of KM CL 9E Ship Construction)
Autor:
Goldy Sandy Gazali, Intan Baroroh
Publikováno v:
Berkala Sainstek, Vol 10, Iss 4, Pp 235-242 (2022)
In shipbuilding work, the risk of delays must be analyzed and anticipated so that such delays do not occur and cause losses for both parties. This study aims to calculate the risk of a shipbuilding project using the Failure Mode and Effect Analysis (
Externí odkaz:
https://doaj.org/article/b39ca72abbf64b0cbe03b0b5b5895dd2
Autor:
Laily Okta Oktafiana, Intan Baroroh
Publikováno v:
Berkala Sainstek, Vol 10, Iss 3, Pp 162-174 (2022)
A ship that is still carrying out sailing activities must always be in a state that is in accordance with the classification and statutory. Maintenance or repair is needed for the ship in order to stay in good condition and fit to sail. In a ship rep
Externí odkaz:
https://doaj.org/article/3dbc32646dfe40db9c98047ef49172d4
Publikováno v:
Kapal, Vol 18, Iss 1, Pp 18-27 (2021)
Construction of a hull generally requires several plates and profile material. Early indications for shipbuilding indicate that in manner, the linear function approach for installed material was 75% to 90%, and waste material was 10% to 25%. This stu
Externí odkaz:
https://doaj.org/article/6108853c0b094d0eb2d19c0cf082042d
Publikováno v:
JURNAL JALASENA. 3:8-17
New shipbuilding projects are required to work quickly according to schedule. For this reason, it is necessary to have a planning and scheduling for shipbuilding so that it is received by the shipowner on time. It is inevitable that in every implemen
Publikováno v:
Kapal, Vol 18, Iss 1, Pp 18-27 (2021)
Construction of a hull generally requires several plates and profile material. Early indications for shipbuilding indicate that in manner, the linear function approach for installed material was 75% to 90%, and waste material was 10% to 25%. This stu
Risk Analysis of the Causes of Delay in Ship Construction (Case Study of KM CL 9E Ship Construction)
Autor:
Intan Baroroh, Goldy Sandy Gazali
Publikováno v:
BERKALA SAINSTEK. 10:235
In shipbuilding work, the risk of delays must be analyzed and anticipated so that such delays do not occur and cause losses for both parties. This study aims to calculate the risk of a shipbuilding project using the Failure Mode and Effect Analysis (
Autor:
Intan Baroroh, Laily Okta Oktafiana
Publikováno v:
BERKALA SAINSTEK. 10:162
A ship that is still carrying out sailing activities must always be in a state that is in accordance with the classification and statutory. Maintenance or repair is needed for the ship in order to stay in good condition and fit to sail. In a ship rep
Publikováno v:
IOP Conference Series: Earth and Environmental Science. 1081:012058
The implementation of the construction of modular construction ships is able to accelerate ship production by up to 50%. However, in practice, delays in the production process can still be found in the engine room module of the modular ship building